Nevada Revised Statutes (Last Updated: December 24, 2014) |
TITLE58 ENERGY; PUBLIC UTILITIES AND SIMILAR ENTITIES |
CHAPTER704. Regulation of Public Utilities Generally |
CONSTRUCTION OF UTILITY FACILITIES: UTILITY ENVIRONMENTAL PROTECTION ACT |
NRS704.891. Reports to be filed with Commission by person holding permit who is not public utility.
-
1. Any person other than a public utility who receives a permit issued by the Commission pursuant to NRS 704.820 to 704.900, inclusive, shall, as provided in subsection 2, file with the Commission reports which contain:
(a) The location, nature and capacity of that facility;
(b) The anticipated date for commercial operation of that facility;
(c) Information regarding whether any public utility in this state has contracted for the purchase of the capacity or other services of that facility; and
(d) Information regarding whether any capacity or other services of that facility is available for purchase by public utilities in this state.
2. The reports required by subsection 1 must be filed:
(a) On or before the date on which construction of a utility facility is commenced; and
(b) On a date not later than:
(1) Twelve months before the scheduled date of commercial operation of that facility; or
(2) Thirty days before the actual date of commercial operation of that facility,
Ê whichever is earlier.
(Added to NRS by 1985, 2297; A 1997, 1917; 2001, 2989)