NRS338.570. Contractor to provide notice concerning progress payments and retainage payments to certain subcontractors and suppliers.
Latest version.
- Within 5 working days after a contractor receives a written request from a subcontractor or supplier of his or her subcontractor or supplier with respect to a subcontract which has not been fully performed, the contractor shall notify the subcontractor or supplier of his or her subcontractor or supplier in writing of the following:
1. The date the contractor made a specified progress payment or retainage payment to his or her subcontractor or supplier;
2. Whether the contractor has paid the entire amount of a specified progress payment or retainage payment to his or her subcontractor or supplier; and
3. The amount withheld by the contractor from a specified progress payment or retainage payment to his or her subcontractor or supplier, if any.
(Added to NRS by 1999, 1987)