Nevada Revised Statutes (Last Updated: December 24, 2014) |
TITLE28 PUBLIC WORKS AND PLANNING |
CHAPTER338. Public Works |
CONTRACTS INVOLVING CONSTRUCTION MANAGERS AT RISK |
NRS338.169. Public body authorized to construct public work by selecting and entering into contracts with construction manager at risk; limitations. [Effective through June 30, 2017.]
-
1. Subject to the provisions of subsection 2, a public body may construct a public work by:
(a) Selecting a construction manager at risk pursuant to the provisions of NRS 338.1691 to 338.1696, inclusive; and
(b) Entering into separate contracts with a construction manager at risk:
(1) For preconstruction services, including, without limitation:
(I) Assisting the public body in determining whether scheduling or constructability problems exist that would delay the construction of the public work;
(II) Estimating the cost of the labor and material for the public work; and
(III) Assisting the public body in determining whether the public work can be constructed within the public body’s budget; and
(2) To construct the public work.
2. A public body in a county whose population is less than 100,000 may enter into contracts with a construction manager at risk pursuant to NRS 338.1685 to 338.16995, inclusive, for the construction of not more than two public works in a calendar year that are discrete projects.
(Added to NRS by 2007, 2891; A 2009, 437; 2011, 3694; 2013, 2974; R 2013, 2986, effective July 1, 2017)